dissamebled-production-order-duplicated.jpgDear All,
I have a client that did a Disassembled production order twice and it has affected their stock account which has affected their P&L report.
How do we reverse the Disassembled production order.
Request clarification before answering.
Hi,
If just the disassembly production order is in planned mode then cancel that else better to go for manual GI and GR for simplicity.
Do it in test by taking a latest backup for checking value impact.