Dear experts:

How to obtain the BOM (Bill of Materials)
The BOM has enabled ECM management, and it is necessary to retrieve the production start and end dates of the BOM components.

Can you provide me with a case study or which tables to use?

KlausWangc_0-1757304988902.png

As shown in the above figure, extract all components of the BOM, and the effective start and end dates of each component need to be specified。

thanks

View Entire Topic
neeraj_putluru
Participant
0 Kudos

hello @KlausWangc ,

STKO --> BOM Header,
STPO --> BOM Item table.

As you have mentioned that you need retrieve all the details of materials so use the table STPO table. Just pass the BOM number as well as the BOM Category since these are unique for each and every BOM, then we can retrieve the details of materials that are assigned if you need header data then you just need to pass the BOM number and BOM category to the STKO. 

Regards,
Neeraj.