I am working with a customer using this SAP Project and Resource Management with S/4HANA Cloud. they use a non-SAP HXM solution. Any recommendation on how to integrate it with SAP Project and Resource Management?
Request clarification before answering.
Hi,
There are multiple options to connect non-SAP 3rd Party HXM solution with the SAP Projects and Resource management. they are
Case 1:
"Non-SAP 3rd party HXM Solution -> SAP Integration Suite -> MDI/MDO -> SAP Projects and Resource Management"
You can refer to the blog that clearly describes the 3rd party integrations with help of Integration suite + MDI/MDO "https://community.sap.com/t5/technology-blogs-by-sap/sap-integration-suite-integration-with-sap-mast... .
Case 2:
Via the API's you can connect the 3rd Party Non-SAP HXM Solution with the S4HC system. Once you have the WF Persons in S4HC you can setup the WF Person replication from S4HC -> MDI/MDO -> SAP P&RM. the step by step process is explained below.
Pre-requisite is 6JO scope is already in scope and activated.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aavantika,
Once you have the basic worker information ( workforce person & employment information) in S/4HANA Cloud, which is brought from 3rd party system. S/4HC already has integration of worker data to SPRM. This is via pre-built integration between S/4HC and SPRM using MDI service.
But please remember that integration is already provided by SAP as part of the 6JO scope.
Regards,
Sai
User | Count |
---|---|
107 | |
39 | |
6 | |
5 | |
5 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.