on 2018 Jan 11 11:49 AM
Hi Experts,
I am running MRP (MD02) during that planned order date is generated reverse the bill of material which is following.(S4 HANA 1709).
Ex:
MAT-Start date-Finish date
FGS-01.01.2018-02.01.2018
SFG3-02.01.2018-03.01.2018
SFG2-03.01.2018-04.01.2018
SFG1-04-01.2018-05-01-2018
ROH-05.01.2018-06.01.2018
But in general manufacturing process will be of ROH-->SFG1-->SFG2-->SFG3-->SFG4-->FGS and start date & end date will be of 01.01.2018-->02.01.2018-->03.01.2018-->04.01.2018-->05.01.2018
how to get the above production order dates after MRP run.