How to exclude LTP run Materials from running MRP

former_member653559
Discoverer
0 Kudos
218

Hello SAP Gurus,

We are running LTP for BOM to create Planned orders and convert them to Purchase requisitions. Also, MRP is running on all materials separately, Is there any standard configuration in SAP to exclude Materials from MRP run for which requisitions are already created in LTP?

Thanks in advance!

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

You can use, user exit M61X0001 for the planning run to exclude material from MRP planning.

Function modules EXIT_SAPLM61C_001 and EXIT_SAPMM61X_001 and you can define parameters like MRP controller, MRP Type need to be plan in MRP or exclude from MRP.

For more details please refer this useful blog on it,

MRP: User exit key & User exit parameter

Best Regards,

R.Brahmankar

former_member653559
Discoverer
0 Kudos

Thanks for your quick response. This definitely works.

But is there a way to use MRP Group in restricting these Materials from MRP run?

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Yes you can use MRP group too as user exit key and parameter.

Best Regards,

R.Brahmankar

Answers (0)