on 2024 Apr 23 1:59 PM
In our system UPA is active and we wnt to enter a project budget with CJ30. This is not possible as we receive the error "Function not possible as UPA is active". so now we need a new solution to enter the projects budget. We know that we can use the financial data import as a work around, but there should be an app to maintain the budget manually.
Request clarification before answering.
Please try implementing SAP note 3399264 - UPA OP2023: Transactions block rollback.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.