on 04-17-2009 1:01 AM
Hi,
Pleases provide me the process to delete the standard cost estimate that i executed in CK11N.
Thanks
Supriya
Hi!
if you are not yet marked or released, you can delete using t.code : CK44.
if you marked/released you can delete std price/planned price using t.code: CKR1. but if you are doing in production system check consistency( only precautionary measure). system will give informative message regarding this. but no problem you can execute it. there are options available in this t.code, you can use based on your reuqirements( future std estimates,current std estimates,previous std estimates)
regs,
ramesh b
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
if u r not relased yet u can re - execute cost by using t.code CK11n if your released first you have to run t.code CKR1 then execute CK11n
Thanks & Regards
Phaneendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
use t.code CKR1
Thanks & Regards
Phaneendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Supriya,
In my understanding even if you have saved the cost estimate made in CK11N,you can carryout a new
costing run,only if its marked or released you have to cancel the same using CKR1 and proceed ahead.
Check and revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.