How to create Matrix value "3" (Greyed) in Shipment cost condition Tcode T_06

prakash_parikh
Participant
0 Kudos
253

Hello Experts,

I am trying to create New shipment cost condition type Transaction Code T_06. Here in Freight Costing Tab Matrix Maintenance field is Greyed Out so I can not put value "3". How to get value "3" ? I can copy another condition having value "3" and can work .But I need what is configuration path or Tcode to get this value? Appreciate your urgent help.

Thanks

Prakash

View Entire Topic
rajiv_trivedi
Participant
0 Kudos

Hi Prakash,

In T_06 freight condition Matrix is set when you click Scale for condition type. If you select one dimension, Matrix will show as "1" If you select three dimensions it will show as "3" Please also maintain scale for each Reference in VS01. This will resolve your issue. There is no other setting for Matrix. If any questions, please revert back.

Thanks

Rajiv Trivedi