cancel
Showing results for 
Search instead for 
Did you mean: 

How to configure the setting so raw material PR is generated by production order?

KS_888
Newcomer
0 Kudos
81

How to configure the setting so raw material PR is generated by production order?

And below is the desired scenario:

Production Order 1 -> RM PR 1

Production Order 2 -> RM PR 2

And other components inside Production 1 and 2 -> consolidated to 1 PR

 

Here is how it is being set up today:

Routing is set as first operation is warehouse operation to withdraw raw material.

Raw material lot size is set to "EX" and MRP runs daily and RM PR is generated.

If Production order 1 and 2 has same date, it is generating a combine PR.

Is there any way we can configure SAP to allow raw material PR to be generated based on each production order? Thank you.

 

 

 

Accepted Solutions (0)

Answers (0)