on 2012 Nov 28 3:51 AM
Hi experts,
I want to close a Purchase Req which created at CJ20N, but i can't set Closed at ME52N.Please help me.
Regards'
Qiao
Request clarification before answering.
Hi,
Before closing PR check for subsequent document PO creation. If exists then delete the line item in PO using ME22N. After that in ME52N delete the line item. In the lower section under tab "Quantities" check against Close.
Inspite of doing all these steps, still system creates another PR since material exists in Project Builder. If you do not want to that material to be procured or no longer required then delete the component in Project builder. By doing all these you are ensuring every thing is deleted properly and no more issue crop up.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Zhang,
In addition to suggestions given by Sudhakar, please check when you are trying to mark Closed indicator in Quantities/Dates tab of PR, same PR which was created for respective component is not open in CJ20N transaction in another screen.
If it is open, you will not be allowed to edit the PR. In such case, close another screen where CJ20N is opened, and retry marking Closed indicator for PR in ME52N.
Regards
Tushar
| User | Count |
|---|---|
| 30 | |
| 16 | |
| 14 | |
| 6 | |
| 5 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.