Good Day

What is the t-Code to change the BOM Components in mass . I need the procedure  to make the changes in the BOM Components at a time for all CODES

Accepted Solutions (1)

Accepted Solutions (1)

former_member209265
Active Contributor

Hi Radhakrishna,

Do with CS20. Select component and it will fetch all the BOM. Then change with the desired component/Qty.

Regards,

Krishnendu.

Former Member
0 Kudos

Hi

Mr. Krishnendu Das

Thank u very much . and i have one more dough How to change the selected  Compound for the SELECTED MATERIALS in MASS 

former_member209265
Active Contributor
0 Kudos


Hi Radhakrishna,

In my knowledge no way is there .

Regards,

Krishnendu.

Former Member
0 Kudos

Hi Krishnendu

Thank u

Answers (4)

Answers (4)

former_member184737
Active Contributor

Hi Radhakrishna,

               Try to check with CEWB for mass change of components in BOM.

Thanks

former_member184666
Active Contributor
0 Kudos

Hi Radhakrishna,

Try using CEWB.

Steps to follow:

  1. Select current work area as BOM item (SAP_ITEM )
  2. On item tab select the component you want to replace & enter plant
  3. Select LOAD BOMs & Tasklist icon.
  4. System will load all the BOM's that have that item. If a Bom has multiple items with same component number , multiple lines of BOM are displayed.
  5. Select the change ( pencil ) icon on the screen
  6. The component columns can now be changed. Ie insert the new component number for each of the bom's.
  7. Click on Save.
  8. System will display message worklist saved.

Thanks & Regards,

Ramagiri

eduardo_hinojosa
Active Contributor

Hi

Krishnendu is right, but see also SAP Note 374807 - New CS20: Validity / logic for further details.

Regards

Eduardo

Message was edited by: Eduardo Hinojosa

former_member230000
Participant
0 Kudos

We have a solution that allows for mass BOM updates. The report has BOMs and the components.

  1. Select components from the main report.

  2. press the mass change icon where you are prompted to select objects that need to be updated.

  3. This results in the component being copied

Former Member
0 Kudos

Hi

Mr. Krishnendu Das

Thank u very much . and i have one more dough How to change the selected Compound for the SELECTED MATERIALS in MASS