on 2022 Jun 27 12:04 PM
How do we assign multiple work centres for one material ?
Request clarification before answering.
Hello
You don't assign a work center directly to the material.
You will create a routing for your material, and this routing will have several operations, each one referring to a different work center.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If Assign Routing with Different Work Centres which control key should be used either PP01 and PP03 Control key for Last Operation.
Which Control key should be assigned for the above activity?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ram,
You can assign the control key depends business requirements, like all operation required confirmation, Milestone confirmation required. auto GR or operation with inspections,
Also if you are assigning control key on Work center as default value that will be automatically copied in routing
Regards
Prasath