Currently we maintain single budget on each work order and and there is request from business to maintain multiple budgets since designs have multiple budgets, how can we can handle multiple budgets on single order.

Accepted Solutions (0)

Answers (3)

Answers (3)

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi

Conceptually it sounds like the Appropriation Request object, it handles multiple versions of cost planning and one is approved at the end. Next the order can be created.

Regards,

Paulo

sanilbhandari
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

As far as I know, there can only be one budget profile assigned to one order type as a standard functionality

Thanks & Regards

Sanil Bhandari

a_meijer
Explorer
0 Kudos

Hi,

To my understanding this isn't possible. At least not with standard SAP functionality. The budget profile attached to PM order type will only accept one budget. Additionally you can only enter supplements or returns.

former_member426924
Discoverer
0 Kudos

Thanks for your inputs. We are planning to set up budget numbers at operation level of the order, later those costs will be settled to an internal order and finally they will interfaces to external systems like BPC, Powerplan and BW. Planning to do a proof of concept.