How the first shortage date is calculated in Monitor material coverage app

RaghavanKathamuthu
Active Contributor
343

I am using Monitor Material Coverage app. But have some doubts. Please explain.

My BOM

RaghavanKathamuthu_4-1724786008556.png

Maintain Time dependent stock app for material PPA24

RaghavanKathamuthu_5-1724786113054.png

This is my output screen from MMC app

RaghavanKathamuthu_0-1724785820948.png

MD04 screen - Material PPA24

RaghavanKathamuthu_1-1724785849133.png

1. How the first shortage date is calculated here for material PPA24?

MD04 for material PPB24

RaghavanKathamuthu_2-1724785948271.png

MD04 for Material PPC24

RaghavanKathamuthu_3-1724785962861.png

2. Why stock availability column is red for PPC24 only even I have the receipts and not for PPA24 & PPB24?

I referred this Link but not getting it.

3. How the below fields/ columns get calculated?

Days' Supply - current stock and the receipt and requirements information included

Stock Day supply - Only stocks and requirements. Not Planned receipts -

The day of the first shortage and the current date are taken into account for this calculation

Intraday Supply = Days Supply + Fractional Coverage on the Day of the First Shortage.

Stock Intraday Supply = Stock Days’ Supply + Fractional Coverage on the Day of the First Shortage.

4. How the below color codes got generated in respective columns.

Maintain Time-Dependent Stock Levels - Safety days of supply, Target days of supply

Red - Current day - First shortage days < SDOS & TDOS

Green -  SDOS < Current day - First shortage days < Target DOS

Yellow - Target DOS < Current day - First shortage days

Please provide your ideas

 

 