on 2024 Feb 07 6:18 AM
Hi All,
As SAP PS consultant, I understand the linkage of SD-PS in milestone billing, however I want to know how we utilise Projects, WBS and networks for Periodic billing process, are there any parameters that needs to be linked from PS side.
Please let me know.
Regards,
Vinita.
Request clarification before answering.
Use Network Activities to create the project schedule then attach Billing Milestones to the Network Activities. As the schedule changes the milestones will automatically be rescheduled.