How does the Cycle Set Sequence work with one Cycle Set in a Multiple Counter Plan?

Accepted Solutions (0)

Answers (2)

Answers (2)

peter_atkin
Active Contributor
0 Kudos

Judd,

Just my guess, but the mutli-counter is just the trigger for the plan, and it will likely trigger the next cycle-set that is due in the maintenance plan.

PeteA

m_waqas
Explorer
0 Kudos

Hi,

You can use multiple counter plan if your pm scheduling is based on 2 or more factors like Running hour and period .

But If you scheduling is based on Running hours only then you can use strategy plan with counter.

Regards