Hello,

can i use a reverse counter in a performance based maintenance plan?

Can i realize it without using user Exit "IMRC0001" ? How do i have to configure the the measuring Points für the maintenacne plan? (Do i have to create more than one Measurment Points?)

Thanks in Advance

Kind regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jens,

Backward counters is not allowed in maintenance plan.

What you can do is you will have 2 counters; one is backward and the other one is forward. Then you are going to create measurement reading transfer between these 2. As you create backward documents for the 1st, system automatically creates forward documents for the 2nd. Then you are going to create a maintenance plan for the 2nd.