Hello Friends

After creating process orders and planned orders, if we want to assign most recent production versions for these documents, we have to do it manually by selecting one by one document in COR3 or MD04 which is very time-consuming.

Is there a standard transaction or program in SAP to process mass number for documents in a few clicks pls ?. If there is nothing currently as a standard, is there a way we can create one pls ?. thanks in advance for your help.

Accepted Solutions (1)

Accepted Solutions (1)

lingaiahvanam
Active Contributor
0 Kudos

Hi Rusheek,

The mass change of production version in process orders or planned orders not supported by SAP standard process.

I would suggest creating an LSMW, BDC (COR2 and MD12) or custom program to change mass production version.

Process order change BAPI - BAPI_PROCORD_CHANGE

Planned order change BAPI - BAPI_PLANNEDORDER_CHANGE

Best Regards,

Lingaiah

Answers (1)

Answers (1)

former_member184509
Participant
0 Kudos

Thank you so much for your help on this, I will take this idea forward.