on 2025 Jan 15 12:40 PM
Hello,
If I have strategy based preventive maintenance plan which includes one maintenance item and which task list include multiple different selected maintenance packets (cycle/interval).
QUESTION: Can I pause and put on hold OIL CHANGE 3 WEE, but still continue VISUAL INSPECTION 1 WEE packet to call order every 1 week?
1. VISUAL INSPECTION 1 WEE
2. OIL CHANGE 3 WEE
Request clarification before answering.
Greetings,
perhaps you can try using offset in strategy package. When a strategy changes you will need to run transaction IP11U to update scheduling.
Below is an example of offset for 10 years of package one. Perhaps try in a test system first.
After running IP11U we get the following result - package one (which is yearly) has been "suspended" for 10 years.
If you want to suspend it for indefinite time then try to use a bigger number - for example 100 (suspended for 100 years).
Best regards, M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 23 | |
| 12 | |
| 6 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.