on 2025 Jan 07 1:16 PM
Hello everyone,
ich have a problem regarding the goods receiving hours.
The goal is to schedule the delivery in accordance to the receiving hours of the respective customer.
The steps i did to achieve this where:
Maintained the goods receiving hours (T-Code: OVSC)
Assigned the Goods receiving hours to the business partner by creating an unloading point and assigned the defined goods receiving hours to the unloading point
Activated the goods receiving hours consideration in the Sales Order Type (T-Code: VOV8)
The the behaviour i expect is the following:
If the entered delivery date in the sales order is outside the timeframe of the defined goods receiving hours, the system should reschedule the order within this timeframe.
For certain reasons, this is not the case. I receive a warning, but the delivery date does not change. I attached a screenshot of the warning message.
Does anyone know why the goods receiving are not included in the delivery scheduling?
I look forward to your answers
Request clarification before answering.
Delivery date in sales order will be calculated based on the Factory Calander ID and It adds Transit Time and Transport Lead time to it
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 33 | |
| 17 | |
| 14 | |
| 13 | |
| 9 | |
| 4 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.