Hi All,
I have scenario where bulk material is issued to contractor against the purchase order using 941 movement and material is under sub contract and same can be seen with MBLB report. My question is how can I show the consumption or goods issue (261 movement) for this material against Preventive maintenance order and breakdown maintenance.
This is related to utility industry where material is issued inn bulk, so that contractor can do the PM and Breakdown maintenance without any hassle.
Request clarification before answering.
Movement type 261 is Goods Issue to Order. It will not come into the picture here as you are issuing your stock to the sub-contractor.