on 2024 Jun 24 1:22 PM
Dear colleagues.
We are searching in MLDOC and MLDOCCCS tables to get the actual cost with component split of a material but it's not posible to restrict values and get the same actual cost than in MLCCSPD transaction.
This material does not have stock because all the produced quantitiy is in WIP and consumed (movs 261/262) in production orders during months.
It seems that there's no way to get the actual cost with cost component split for a mont/year/kalnr if there is no stock.
Do you know any function module of the needed filters to get the amount for the cost lot size?
Thanks in advance and best regards,
Request clarification before answering.