on 2007 Jul 20 2:51 PM
Hello,
How to configure the Freight Conditions in Sub contracting??
Shall i use the accural or Account Key for the freight condition.
How system behaves when the freight is posted against the Subcontracting PO??
Freight has to added on to the Material Cost while posting Planned Delivery Costs?
Please explain
Thanxs & Regards,
Kumar.
Hi
Freight w.r.t. subcontracting order will be treated similar to a standard order.
You can make use the standard FR1.
All the accounting will be posted during goods receipt to the extent of qty received. The freight also gets inventorized as like components cost and conversion cost.
warm regards
sairam akundi