Forbidden Material Purchase Requisition for WBS through Status Profile

vijji_vj
Explorer
0 Kudos
380

Dear Gurus,

Greetings...!

Hope everyone is safe and staying home.

I have configured a WBS status profile with initial status 'Material purchase requisition' as 'Forbidden', but when I tried creating a material PR through network activity, it was created. When I am trying to create manually through ME51N account assigning the WBS with my configured status profile, then it is throwing the error. Could you guide on what can be done to apply the same to PRs created through Project.


Regards,

Vijay.

View Entire Topic
kenmelching
Active Contributor

Duplicate your user status profile on the Network.

vijji_vj
Explorer
0 Kudos

Dear Ken sir,

I have did the same, applied the same to Network & Activity and created new Project, but still Network Activity is allowing to create PR. Kindly advise.

Regards,

Vijay. M