Dear Gurus,
Greetings...!
Hope everyone is safe and staying home.
I have configured a WBS status profile with initial status 'Material purchase requisition' as 'Forbidden', but when I tried creating a material PR through network activity, it was created. When I am trying to create manually through ME51N account assigning the WBS with my configured status profile, then it is throwing the error. Could you guide on what can be done to apply the same to PRs created through Project.
Regards,
Vijay.
Request clarification before answering.
Duplicate your user status profile on the Network.