cancel
Showing results for 
Search instead for 
Did you mean: 

For lower materials, purchase requisitions are generating , while creating the production order

MudiamReddy
Participant
0 Kudos
192

Hi All,

While creating the production order, for lower level BOM components, purchase requisitions are generating with the direct procurement.

But for lower level materials, we have not activated the special procurement at the material master, BOM and at over all plant parameters.

Please let me know is there any other place, where we can maintain the special procurement to get the direct procurement for lower materials.

Thanks

Bhage

View Entire Topic
MudiamReddy
Participant
0 Kudos

Hi Behan ,

Thanks for the given link.

It is completely related to PP-SD integration scenario and assemble to order process. But in my scenario, planning strategy is 10, requirement type is LSF. So, it is not linked to my issue.

With respect to my scenario, lower level components has to consider the available stock, instead of creating the purchase requisitions with direct procurement.

Please refer to the below screen for your reference.