Dear Expert,
There is a requirement from my Client regarding Factory Calendar.
Production runs for 5 Days a week (Mon-Friday) but Maintenance runs 6 Days a week (Mon-Sat).
Maintenance Team wants system to generate Orders on Saturday as well from Maintenance Plans.
If a separate Factory Calendar (with 6 Working Days) is created for Maintenance, is there any potential impact on Production or PPDS?
Regards,
S Kumar
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raheel,
Thanks for the links.
It is now clear that a separate Factory Calendar for Plant Maintenance won't hamper with Plant Level Factory Calendar.
I need to now assign this Calendar to Work Center as well as Maintenance Plan (Scheduling Indicator-Factory Calendar).
Is my understanding correct?