Hi Experts,
I am working on S/4 HANA 1809, when i execute Manage work centre queue app, I can see the Work Centre but it does not gives any values.
1. BP is created 10010, User ID and Personal Number is assigned to it.
2. Assigned Person to Work Centre (HRMS) A10
3. Assigned the BP 10010 in Manage User Setting app with Work Centre A10 and Plant.
I have lot of Operations open, released and confirmed with Work Centre A10 in the back end.
Do i miss anything in the progress, is it a bug or some data is missing ? Kindly advice.
Regards
Terence
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi,
I have raised a OSS to SAP. Production Orders with Status MPE are only seen in this app.
Production Engineering and Operations was not part of Standard PP, so additional agreements are required.
For more information, raise a OSS.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
12 | |
7 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.