on 2021 Oct 27 10:42 AM
Hello Team
We are having one scenario, we are putting last operation as a external processing with Auto goods receipt and with the milestone confirmation.
But then also the Auto Goods receipt not happening, is it that this functionality not work for the external processing ?
and auto GR will only happen in Internal Processing.
Br, Kiran U
Request clarification before answering.
Hello
Automatic goods receipt will only happen when you post a confirmation to this operation, for example, using transaction CO11N.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kiran,
You can activate the auto GR in the below ways,
1. With a Control key which is having the Auto GR Ticked in PI03.
2. Other with Scheduling profile (OPKP).
Thanks,
Sundhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
39 | |
8 | |
6 | |
5 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.