Boss can any one tell me the Exact process of EXTERNAL CALIBRATION in SAP PM???
thanks you
1. Create Equipment
2. Create Task list
3. Create Maintenance order
4. Create PO from PR
5. Do the Service entry sheet
6. Do the TECO
7. Vendor Invoice & Payment
8. Settlement
9. Business Completion
Note: Try to avoid colloquial language & capital letters in forums
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ronak,
Please search in previous threads before posting an issue.It will save your time also.Refer the thread below.
Please follow below steps for for external calibration
For external calibration do following steps :
1) Create general task list for external calibration Equipment (IA11,IA01,IA05)
2) Create single cycle plan (IP41)
3) Schedule the maintenance plan (IP10)
4) Generation of Inspection lot and Purchase Requisition (IW32 / QA32)
5) Create Service Purchase Order from Purchase Requisition.(ME21N)
6) Confirm service entry sheet (ML81N)
7) Process inspection lot and UD (QA32)
Settlement of Calibration Order (KO88)
9) Business Completion / Close order (IW32)
You can use PM03 control key.