Dear All; I exactly need the sales order to be excluded from the MRP planning but continue to do the stock verification as the CP distribution type does, the detail is that with the CN distribution type it does not perform the verification and it needs to be done even excluding the order from the planning

Accepted Solutions (0)

Answers (1)

Answers (1)

Suryaprakash13
Active Participant
0 Likes

Dear @EPIRELA,

To remove the sales order from the MRP Run, create a new z schedule category and in the transaction flow of the item category do the below:

  • Check the Availability 
  • Uncheck the Requirement/Assembly

Hope this helps !!!