EXCLUDE PROJECT STOCK MRP

Former Member
0 Kudos

DEAR GURU

MY QUESTION IS I WANT TO EXCLUDE PROJECT STOCK WITH INDICATOR Q FROM MRP.

SHOULD I TRY THE STORAGE LOCATION METHOD BY EXCLUDING A PARTICULAR LOCATION FROM MRP?

OR

IS THERE ANY WAT TO DO SO....PLEASE SUGGEST

Accepted Solutions (1)

Accepted Solutions (1)

sundaresan_velayudam
Active Contributor
0 Kudos

Dear,

In IMG>production planning>MRP--> Planning -->stocks -->define availabilty of stock In transger/blocked/restricted stock

un check the restricted stock

and then try to run MRP

or IN OPPQ -->Available stock uncheck the restricted use stock

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

madlercm
Active Contributor
0 Kudos

1- there's a user exit (M61X0001) that will allow you to filter the materials planned by MRP, maybe you can use it to filter projects.

2- there's a BADI (BAdI MD_CHANGE_MRP_DATA) that potentialy can be used to filter out project related MRP data.

In any case project planning is done in the individual segment of WBS, and that should not impact in any way the general stock planning. In displays like MD04/MD05 you can use a display filter not to see the WBS segments.

Former Member
0 Kudos

Hi ,

Just my 2 cent idea ,

For PS MRP run MD51, system checks the available quantity of PS stock against specific WBS.

Please note that the special stock indicator Q for project stock will not consider existing stock.

Goto Run MD51 and then take MRP run again in MD02 and check the result.

I would suggest you use Master Data Level to excluded because is easier to control but depend on your business scenario.

As if you using Storage location , you need to have specific location only for PS and you need to involve Material transfer among.

TQ.