Hi Experts ,

Our Customer is using IBP and S4HANA. At the moment we have some critical products that are going to be integrated to IBP via CPI-DS from S4HANA for planning. But what i understand we don't have any filter criteria in S4HANA to exclude products which are already plan in IBP and should not get re-planned again in S4HANA by MRP LIVE / PPDS for S4HANA. By any chance anyone faced similar type of situation and how it can be handled.Will there be any customization required or something standard can restrict product being from getting re-planned by MRP LIVE.

Thanks in advance

Ashwin

Accepted Solutions (0)

Answers (2)

Answers (2)

jessica_li
Advisor
Advisor
0 Kudos

Hello,
Yes, you are right. I don't think there is no field in S/4HANA to log if material has been executed in IBP already. Caetano suggests to change MRP type to ND. If do so, then the material is not participating in MRP in S/4HANA at all. Is this your requirement? If you still want it to run MRP if no IBP planning executed?


BR,
Jessica

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

If you set MRP type ND, then it won't be planned by MRP Live.

Regards,

Caetano