on 2016 Aug 25 7:17 AM
Hi
I'm searching the forum for similar discussions and tried program SDRQCR21 already but no luck.
there is a requirement from sales order for 59 pc and a production order exists arleady to supply 59. but still MRP is proposing a new plnd order for 59 pc which leads to an excess of 59 finally. I've tried to delete the production order and run MRP and nothing is proposed, which is good. then I convert the plnd order to a production order and run MRP, again a new plnd order is created. what can be wrong here?
kljf
Hello,
Which MTO planning strategy are you using?
Does production and planned order have an assignment of sales order?
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Could you please share the screen shot of planning strategy?
Also is there any changes in Sales order line time?
Also check the rescheduling customizing on transaction OMDW for rescheduling horizon and fixed receipts. You should ensure that the lead time of the Materials in the material master are as realistic as possible.
Please refer this wiki page,
What is rescheduling and how does it work - ERP Manufacturing (PP) - SCN Wiki
Best Regards,
R.Brahmankar