Hi Everyone,

I'm facing strange behaviour in Time Evaluation with my newly prepared schedule.

The client wanted a schedule with the following settings:

  • Planned working hours - 4 hours [4 hours counted as full time in this case]
  • Planned working time - 6 AM and 6 PM [An employee should have the possibility to start the work between 6 AM and 2 PM]

The problem appears during the time evaluation. SAP counts the time before the start of the work as an absence, and I don't know why?

Could you give me a hint where should I search for the cause?

Accepted Solutions (0)

Answers (1)

Answers (1)

hrmanagerde
Active Participant
0 Kudos

Hi Jakub,

I think the only way to find out is to run PT60 with "Display log" switched on and go through the schema.

Good luck!

BR,

Armin