on 2023 Dec 19 5:11 PM
Hi all,
I have a problem when run MRP for PS by MD51. I have a project structure below:
Project definition: PEN-00210
1.WBS element: PEN-00210.01.007 (Main WBS Element)
Network: 101
Activity: 101 - 10 (material A, quantity = 10) (Header Material)
2.WBS element: PEN-00210.01.007.01 (1st Sub-WBS Element)
Network: 102
Activity: 102 - 10 (material B, quantity = 10) (HALB Material).
WBS element: PEN-00210.01.007.02 (2nd Sub-WBS Element)
Network: 103
Activity: 103 - 10 (material C, quantity = 15) (HALB Material)
My questions is:-
1. When I run MRP by MD51 for WBS Element PEN-00210.01.007, System Generate 5 planned orders. For Example,
a. 1st planned order - Material A wrt PEN-00210.01.007 (Main WBS Element) for 10 qty. (which is OK).
b. 2nd Planned Order - Material B wrt PEN-00210.01.007 (main WBS Element) for 10 qty (that is not ok i want system will create Plan order only wrt their WBS Element i.e. PEN-00210.01.007.01 (1st Sub-WBS Element).
c. 3rd Planned Order - Material B wrt PEN-00210.01.007.01 (1st Sub-WBS Element) for 5 qty (That is not ok. System generate plan order wrt to their WBS element but why for 5 qty....?)
d. same for C materials.
Basically I want that system generate plan orders wrt to their particular WBS Elements but I don't know how System generate 2 planned orders for 1 material which is for their Main WBS element & also for their Sub-WBS Element.
Please Help to resolve this problem
Thanks.
Request clarification before answering.
Thanks for the reply sir,
I have assigned finished material to parent WBS element & semi finished materials to sub WBS elements. I have assigned Network activities to WBS element.
Project Structure -
MRP Results With hierarchy -
Total Requirement for header material is 2 EA
Results for Semi finished materials 698101652
System generate 1st planned order wrt Main WBS element PEN-00210.01.007 for (8 qyt). & 2nd planned order wrt to their WBS element PEN-00210.01.007.01 (4 qyt.).
Please Find Screen shot of CSP1 for more Clarification.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What are the WBS assignments for the Network Activities? Are you assigning the Network Activities or the Network Headers to a WBS? Please attach screen shots as well of the project objects and the MRP results.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
9 | |
9 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.