on 2024 Feb 19 1:39 AM
Hi,
There is plan cost/revenue can be uploaded to project.
Example:
Planned Revenue : $ 150,000 ; Planned Cost : $ 100,000
The project started with POC. However, when the project started half way, total cost was overspent. The expected cost will increase to $150,000. Project Manager plan to update the expected cost to $200,000
What is the best practice to handle this scenario? How to post provision of lost amount?
thank you.
Request clarification before answering.
Hi Chong,
In S/4HANA Cloud, Public Edition. the planning of project costs is majorly done via the excel upload. the planning of costs is done at WBS element level period wise. As per the below template available you can plan the costs for whichever period you wanted by re uploading the excel with the additional amounts.
Regards,
Sai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
7 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.