Hello,
The sorting of individual project segments is carried out according to the object number of the WBS element, however the planning time fence always refers to the net or gross segment.
MD04/MD05 display the MRP element in thir individual segment, this is as per standard SAP system design.
So End of Planning Time Fence will appear in net/gross segment and Project or sales order MTO appear in individual segment separately.
For more details please refer SAP note 2506125 - MD04 List not sorted based on requirement date
and 27876 - Planning time fence (man.firming/display/segments)
Best Regards,
R.Brahmankar