EAM planning bucket

castin
Participant
0 Kudos
584

Setup EAM I have followed BPE 4HI and create planning bucket for Technical object..

  • Duration 7 days
  • recurrence - weekly
  • recures every week
  • buckets in advance 5
  • assign technical object 1234

When orders are ready for schedle and run the Maintenance backlog overview and I select the Bucket for that Technincal obejct and look forward in advance 5 I see nothing. the order is set for this week.

I have no clue what is wrong. THis seems like strange way to manage what orders are ready to be schedule

 

Any insight into why nothig shows would be helpful. Or a better way to see if parts are on order with PO and it cant be scheduled it. I guess I expected a better view.

View Entire Topic
sammar81
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi, 

Check your plant and other scope details maintained for the planning bucket. Are there orders created for the technical object 1234 in your system? The data is picked based on the scope defined while creating the bucket. 

Refer to the SAP help documentation on understanding the concept of Planning Buckets. 

https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/e72f747389b340229f7fa343975bfa57/9f8af92329054abb981... 

hope it helps

Sammar