on 2025 Feb 06 6:09 AM
Hi Experts,
Please help me on this issue.
In some cases duplicate plan orders has been created for same sales order line item. Please see below details.
Material type :- KMAT
Strategy Group :- 25
Lot Sizing Procedure :- Ex
Maximum/Minimum lot size :- "0"
Can anyone let me know the reasons behind this?
Thank you.
Request clarification before answering.
Hello,
I think you should provide more details like the quantity of the production order and informations in MD04.
However, i don't know if the SO's quantity is 50 and it was splitted into 2 planned orders one planned for 30/01/2025 and one for 31/01/2025 due to capacity availability of the work centers during these days.
Regards,
Houda.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Houda,
FYI & please refer below available details
The user has converted the plan orders to production order . Therefore unable to share the details in MD04.
However please see the below screen shot of COOIS report and assignment tab of production orders . You can see the duplicated production orders for same Sales Order Line Item (20). If you need more details please let me know.
See the different planned orders for same line item in the assignment tab.
1st Production Order
2nd Production Order
User | Count |
---|---|
100 | |
12 | |
10 | |
8 | |
6 | |
4 | |
4 | |
4 | |
4 | |
3 |