DS Alternative resources with different run rates

jeswe
Discoverer
0 Kudos
490

Hi

I am working in the process industry and are using PP-PI

We have a need for alternative resource with different times.

Beside that we need drag and drop functionality. So I would need to use the "classes and characteristics" method.

Are there a standard way to give these alternative resource different run rates?

If not, then any smart ideas 🙂

View Entire Topic
Sasi2005
Contributor
0 Kudos

Hi Jesper,

If you are using the class and characteristic method, you would need to use the BADI with the logic so that the different run rates are modelled. Standard doesn't allow different run rates to be modelled.

Regards

Sasi