Hi Guru's,
As per my business scenario, i am creating project with WBSE, Activities and BOM.
By using the reference points, i am transferring the BOM to Project, then executing MRP run (MD51).
But after MRP run i found that multiple PR's generated for the same Material.
Please find my BOM structure
BOM-->Assembly + raw material
Assembly is consists of
Sub-Assembly+ 2 raw materials
Sub-Assembly consists of
1 Raw Material.
as per this i should have 4 PR's after MRP but system is generating 8 PR's.
Please tell me where i am doing wrong
Regards,
Rao
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hello,
Greetings of the day !!
Double PR has been generated after MRP run. Although the material which got two PR generated had got only 1 dependent requirement.
We have maintained one material data as Procurement type as F & Special procurement blank For other material, Procurement type as F & Special procurement 30.
Can anyone help me on this which is top Priority?
Thank You.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
16 | |
9 | |
7 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.