‎2024 Jun 04 11:30 PM - edited ‎2024 Jun 04 11:31 PM
Hi Folks,
We are working on MM deletions. One of the checks is to ensure there are no orders, including planned orders (STPOs). Currently, there are STPOs for every material I want to delete.
The other conditions are as follows:
Is an MRP-run expected to or able to rid the system of the planned orders (STPOs)?
Thank you for your input.
Kind Regards,
PM
Request clarification before answering.
Hello @PMoyo
MRP will delete planned orders if they are not needed anymore and if they are not fixed.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @PMoyo There are no other conditions. MRP will delete superfluous planned orders if they are not fixed. If they are fixed, you will get an MRP exception, telling you that the planned orders are not needed and should be cancelled/deleted.
| User | Count |
|---|---|
| 35 | |
| 26 | |
| 21 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.