Hi ,

I have a scenario where we are using DIEN materials for services.

Now if the work order is performed by a external vendor, then I'd add a DIEN material in the component section.

But my question is what control key should be used in the operation?

Can PM01 be used along with DIEN material, but the operation is performed by external vendor so why do time confirmation?

And if PM02 or PM03 is added it would create 2 PRs ( one from PM02/PM03 control key & one from DIEN material as it's non stock), which is not right approach.

Or could u suggest another approach by using DIEN material in work order.

Would appreciate your help in this.

Thanks

Kumar

Accepted Solutions (1)

Accepted Solutions (1)

preetirai1984
Participant

Hi,

Dien material type is for SD module where to capture the outgoing tax/excise need to have material number

In plant maintenance if u wanted to use dien them control key PM01 to use. And process with dien material type will be similar like PM02 where no service entry sheet will come but directly GR.

Regards, Preeti

abilashk05
Explorer
0 Kudos

Hi Preeti,

Thanks for your reply.

I wanted to understand if I use PM01, then would time confirmation be necessary if planned effort is not entered (along using DIEN material)?

You know since the operation is performed by external vendor and PM01 is for internal labor

Thanks

Kumar

Answers (2)

Answers (2)

Neeraj_Jain
Active Contributor

Hello abilashk05,

Please refer below SAP thread. Hope it's clarifies your query

https://answers.sap.com/questions/13806689/dien-material-type-in-pm-order.html

If satisfied please accept the answer.

Regards,

Neeraj Jain

abilashk05
Explorer
0 Kudos

hi Neeraj,

Thanks for your reply.

But my question is regarding what control key could be used if DIEN material is used.

If PM01 control key along with DIEN material is used and no planned effort entered in the order, can I proceed to Teco with GR & without time confirmation? Any impact during settlement?

Thanks

Kumar

preetirai1984
Participant
0 Kudos

Hi,

Confirmation required or optional depends on your control key PM01 config setting and that is irrespective of dien or any other material type.

Please check what setting you have for your client ortherwise can go for customised control key where confirmation will not be required.

Regards,

Preeti