Determing of the Scheduled release date

sapmaestro199728
Discoverer
0 Likes
585

Hi guys,

I have a question, maybe some of you guys know the answer:

I am trying to find out how the so called "Scheduled release date" is determined (see the following attachement).
The date can be found for example in the transaction CO03 in the "General" data in the row "Release".

scheduled-release-date.png

Does anybody know how the date is determined?
We are using a SAP ERP system and also an external SAP APO system, if this is helpful.

Thanks in advance!

BR Thomas

Accepted Solutions (1)

Accepted Solutions (1)

Corey
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi thomasclein

It depends on the release period maintained in scheduling margin key in MRP view2 of material master.
You may also refer to this online help.
https://help.sap.com/saphelp_erp60_sp/helpdata/en/df/01b753128eb44ce10000000a174cb4/content.htm?no_c...

Best regards,
Corey

sapmaestro199728
Discoverer
0 Likes

Hi corey.yu ,

okay, thanks for information! 🙂

BR Thomas