on 2023 Jun 14 10:10 AM
Hi,
is it possible to keep the functional area of the "sender" psp (overhead), if I am settle the psp to another revenue project?
Right now, I am getting the functional area of the receiver psp or if the receiver psps doesn't have a functional area, I am getting the dummy functional area.
I know that this is possible in the universal allocation but I want to achieve this for the project settlement as well.
Is there a configuration step in the sscui or can i create a substitution role for this?
BR
Request clarification before answering.
Hi Marie,
Suggest you to read this part of documentation:
Regarding settlements: A settlement always takes the data from the sender side. If the sender data (for example, an order) has a functional area on the sender totals, this functional area is taken and no derivation is needed. On the receiver side (for example, a cost center), the functional area derivation does take place.
Best Regards,
Owen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
13 | |
11 | |
5 | |
5 | |
5 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.