on 2016 Feb 10 4:13 PM
Hi,
We use an upload program to create PIR.
BAPI_REQUIREMENTS_CREATE is used in the upload program.
Issue:
The MRP does not create dependent requirements when PIR is created using program. I get the error "BOM not selected" Exception message 52.
Where as, MRP creates dependent requirement when PIR is created manually using MD61.
Please suggest a solution. Thanks
Request clarification before answering.
Hello
The problem here is with the planned order BOM explosion. Are you sending any different parameter that could influence the BOM explosion when the PIR is created with the BAPI? Maybe a production version or the validity can be different...
I suggest you to read carefully the blog and make sure that the notes suggested are implemented on your system.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 29 | |
| 14 | |
| 14 | |
| 6 | |
| 5 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.