Delivery rescheduled during packing - 2023

nayaramr
Member
0 Kudos
369

Hello, I am a basic user, but trying to figure things out so I can present a potential solution to management.

SAP was rescheduling Goods Issue date when handling units were added, but it only happened for customers that had transit time built into the customer master. This caused shipments to be sent earlier than needed.

I saw note 350462, but also saw a comment that says it might not work for packing materials that are stock managed (which ours are). That post was back in 2010, so I was wondering if 13 years later there may have been updates or other solutions to this issue?

Thank you in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

molina_e_1
Newcomer
0 Kudos

Also has the same problem. @nayaramr were you able to find a better way to solve your case?