cancel
Showing results for 
Search instead for 
Did you mean: 

Delivery from project GI movement type

jcision
Explorer
524

Dear SAP experts,

When using delivery from project (CNS0), delivery type LP, the standard Movement type for GI is 281(Q).

For a customer this needs to be changed to 601(Q) for the COGS split.

Valuated project stock is in use.

Is there a way in customizing to change the GI movement type only for delivery from project?

Thanks for your help.

Accepted Solutions (0)

Answers (2)

Answers (2)

gokul_pillai
Discoverer

Hi,

Check t-code OPT1 and try changing the movement type to the one you want the system to derive when using CNS0.

Let us know if that helps.

Thanks,

Gokul

jcision
Explorer
0 Kudos

Hello Gokul,


Thanks for your answer. Unfortunately this will not solve the issue, the delivery is still picking up 281(Q). Also I believe when chaning OPT1 you are not changing this only for delivery from project but also for normal goods issue to network.

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Since the Delivery is being created in reference to the Project and not a Sales Order you need to use the 281 Movement Type so the costs properly flow to the project. See if you can apply your COGS split settings to this movement type.

jcision
Explorer
0 Kudos

Hello Ken,

Thanks for your reply. I believe you are right that delivery from project always picks 281. Will check if the COGS Split can be applied to this movement type. Will let you know the results.

jcision
Explorer
0 Kudos

I can confirm that 281 is hard coded and can't be changed. We will apply the COGS split to Movement type 281 and create a new movement type for normal consumption