I have check in MMBE there is enough with sub contracting vendor , but still I am getting the error.But when i do migo for PO with single line items i dont get any error
Regard
Nabil
Edited by: sayednabil on Apr 20, 2011 12:43 PM
Request clarification before answering.
Another important points i like to suggest is
Do not change BOM until all materials send to
vendor were goods receipted,because while GR material system will take current BOM qty for consumption.
Also block BOM component(In po,material data) from user access,by creating screen variant,this will
also prevent changing BOM child quantities from purchase order.
You may also find material sent to subcontractor(Requirements field) by clicking components icon in material
data tab of p.o,material receipted(Withdrawal Qty).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 36 | |
| 27 | |
| 20 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.